Arbitration in India is governed by the Arbitration and Conciliation Act, 1996, as amended in 2015, 2019 and 2021. It is a private, binding method of resolving disputes in which the parties choose an arbitral tribunal instead of going to a civil court, and the resulting award is enforced like a decree. Arbitration clauses are now common in commercial contracts, partnership deeds, leases, construction and supply agreements and franchise arrangements. This guide explains, section by section, how an arbitration starts, how the arbitrator is appointed, the time limits for the award, how an award is challenged and enforced, and the leading Supreme Court decisions that every party should know.

Core Rule: Courts intervene in arbitration only where Part I of the Act provides for it (Section 5). Most disputes about the tribunal’s jurisdiction are decided first by the tribunal itself (Section 16), and the award can be questioned only on the limited grounds in Section 34.

What Is Arbitration?

Arbitration is the resolution of a dispute by one or more arbitrators chosen by, or for, the parties under an agreement to arbitrate. It may be ad hoc, where the parties and the tribunal run the proceedings themselves, or institutional, where an arbitral institution administers it under its rules (for example, the Delhi International Arbitration Centre attached to the Delhi High Court). An arbitration is “international commercial arbitration” where at least one party is a foreign national, body corporate or government; otherwise it is domestic.

The 1996 Act is in parts: Part I deals with arbitrations seated in India, Part II with enforcement of certain foreign awards, and Part III with conciliation. The Act was substantially amended by Act 3 of 2016 (in force from 23.10.2015) and Act 33 of 2019 (from 30.08.2019), which introduced timelines and stronger rules on the independence of arbitrators.

The Arbitration Agreement (Section 7)

An arbitration agreement is an agreement to submit to arbitration all or certain disputes arising in respect of a defined legal relationship, whether contractual or not. It may be a clause in a contract or a separate agreement, and it must be in writing. It is in writing if it is contained in a document signed by the parties, in an exchange of letters or other means of telecommunication “including communication through electronic means” which provide a record of the agreement, or in an exchange of statements of claim and defence in which one party alleges it and the other does not deny it. A reference in a contract to a document containing an arbitration clause also constitutes an arbitration agreement if the reference makes that clause part of the contract.

When a suit is filed despite an arbitration clause, Section 8 obliges the court to refer the parties to arbitration if a party applies not later than the date of submitting his first statement on the substance of the dispute, unless it finds that prima facie no valid arbitration agreement exists. The application must be accompanied by the original agreement or a certified copy.

Relevant Statutory Text
(1) In this Part, “arbitration agreement” means an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not. (2) An arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement. (3) An arbitration agreement shall be in writing.
— Section 7(1)–(3), Arbitration and Conciliation Act, 1996 (India Code)

Appointing the Arbitrator (Sections 11 & 12)

The parties are free to agree on the procedure for appointment. If they cannot — for example, where one party fails to appoint within thirty days of a request, or the parties fail to agree on a sole arbitrator within thirty days — the appointment is made, on request, by the High Court (or the Supreme Court in international commercial arbitration) or any person or institution designated by such Court. At this stage the Court confines itself to examining the existence of an arbitration agreement.

Before appointment, a prospective arbitrator must disclose in writing any circumstances likely to give rise to justifiable doubts about independence or impartiality, and his ability to complete the arbitration within twelve months (Section 12(1)). The Fifth Schedule guides that assessment; persons falling within the Seventh Schedule are ineligible unless the parties, after disputes arise, waive it by an express written agreement. The Supreme Court has held that a party interested in the outcome cannot unilaterally appoint a sole arbitrator (Perkins Eastman, 2019), and a Constitution Bench in CORE v. ECI-SPIC-SMO-MCML (2024) held unilateral appointment clauses in public-private contracts violative of Article 14, applying its ruling prospectively to appointments made after 8 November 2024.

Interim Relief — Court and Tribunal (Sections 9 & 17)

A party may apply to the Court under Section 9 before or during arbitral proceedings, or after the award but before it is enforced, for interim measures such as preservation or sale of goods, securing the amount in dispute, detention or inspection of property, an interim injunction or the appointment of a receiver. Once the tribunal is constituted, the Court ordinarily does not entertain a Section 9 application unless the remedy before the tribunal would not be efficacious.

The arbitral tribunal itself can grant similar interim measures under Section 17 during the proceedings, and its orders are enforceable as if they were orders of the Court. In practice, urgent pre-arbitration relief is sought from the Court, and later relief from the tribunal.

Time Limits for the Award (Sections 23, 29A & 29B)

Statements of claim and defence must be completed within six months from the date the arbitrator (or all the arbitrators) received written notice of appointment (Section 23(4)). In matters other than international commercial arbitration, the award must be made within twelve months from the completion of pleadings (Section 29A(1)). The parties may by consent extend this by up to six months; any further extension can only be granted by the Court for sufficient cause, failing which the arbitrator’s mandate terminates. Where delay is attributable to the tribunal, the Court may reduce the arbitrator’s fees by up to five per cent for each month of delay.

Under Section 29B, parties may agree in writing to a fast-track procedure, in which the tribunal (which the parties may agree shall be a sole arbitrator) decides the dispute on written pleadings, documents and submissions without an oral hearing unless needed, and makes the award within six months of entering upon the reference.

StageProvisionTime limit
Appointment by other partySection 11(4)–(5)30 days from request; else Court / designated institution
PleadingsSection 23(4)6 months from arbitrator’s notice of appointment
Award (domestic)Section 29A(1)12 months from completion of pleadings
Extension by consentSection 29A(3)Up to 6 months more
Further extensionSection 29A(4)–(5)Only by the Court, for sufficient cause
Challenge to awardSection 34(3)3 months from receipt + up to 30 days on sufficient cause

Source: Arbitration and Conciliation Act, 1996 as displayed on India Code (checked 01.10.2026).

Challenging and Enforcing an Award (Sections 34, 36 & 37)

An award can be set aside only on the grounds in Section 34: incapacity of a party; invalid arbitration agreement; lack of proper notice or inability to present one’s case; the award dealing with matters beyond the submission; improper composition of the tribunal or procedure; non-arbitrable subject matter; or conflict with the public policy of India. In domestic arbitration, an award may also be set aside for patent illegality appearing on the face of the award, but not merely for an erroneous application of law or by re-appreciating evidence. The application must be filed within three months of receiving the award, extendable by thirty days, but not thereafter.

Filing a Section 34 petition does not by itself stay the award (Section 36(2)); a separate application for stay must be made, and for money awards the Court has regard to the CPC provisions on stay of money decrees — usually requiring a deposit or security. Once the time for challenge expires, the award is enforced under the CPC as if it were a decree. Appeals lie only against the orders listed in Section 37. In Gayatri Balasamy v. ISG Novasoft (2025), a Constitution Bench held that courts have a limited power to modify an award — by severing an invalid part, correcting clerical or computational errors, modifying post-award interest in some circumstances, and under Article 142 with great caution.

Estimate arbitrator fees: use our Arbitrator Fee Calculator, based on the Fourth Schedule to the Act, before you invoke arbitration.

Indicative Timeline

Day 1
Notice invoking arbitration
The arbitral proceedings commence on the date the respondent receives the request to refer the dispute to arbitration (Section 21).
Day 30
Appointment
If the other side does not appoint or agree within 30 days, apply to the High Court / designated institution under Section 11.
6 months
Pleadings
Statement of claim, defence and any counter-claim to be completed within six months of the tribunal’s notice of appointment (Section 23(4)).
12 + 6 months
Award
Award within 12 months of completion of pleadings; up to 6 months more by consent; further only by Court order (Section 29A).

Arbitration — Step by Step

1
Read the arbitration clause
Check the seat or venue, number of arbitrators, appointment procedure, institutional rules, governing law and any pre-arbitration steps such as negotiation or mediation. Ensure the agreement is properly stamped before relying on it in court proceedings.
2
Send a notice invoking arbitration
Describe the dispute, the claims and the relief sought, and propose an arbitrator or call upon the other party to appoint or agree within thirty days. Keep proof of delivery — the date of receipt is the commencement of proceedings for limitation (Section 21, read with Section 43).
3
Seek urgent interim relief if needed
If assets may be dissipated or the subject matter may be altered, apply to the Court under Section 9 before the tribunal is constituted; arbitral proceedings must then be commenced promptly.
4
Constitute the tribunal
Appoint by agreement, or apply under Section 11 if the other side fails to act. Obtain the arbitrator’s written disclosure under Section 12 and raise any objection within the time allowed.
5
Plead, prove and argue
File the statement of claim with documents; the respondent files the defence and any counter-claim. Jurisdictional objections must be raised not later than the statement of defence (Section 16(2)). Evidence and hearings follow, and the award is made within the Section 29A timeline.
6
Challenge or enforce
The losing party may file a Section 34 petition within three months (plus up to thirty days). The winning party may execute the award as a decree once the challenge period expires or if no stay is granted.

Documents Required

✓The contract or separate agreement containing the arbitration clause (original or certified copy)
✓Notice invoking arbitration with proof of delivery
✓Correspondence showing the dispute and any refusal
✓Statement of claim with supporting documents and calculations
✓Proof of payment of stamp duty on the agreement, where applicable
✓Arbitrator’s Section 12 disclosure and acceptance
✓Power of attorney / board resolution authorising the representative

Recent Developments

8 Nov 2024
CORE — unilateral appointments
Constitution Bench holds a party cannot unilaterally appoint a sole arbitrator; unilateral clauses in public-private contracts violate Article 14 (prospective).
30 Apr 2025
Gayatri Balasamy — limited power to modify
Constitution Bench recognises a limited power of courts under Sections 34 and 37 to modify awards.

Landmark & Recent Judgments

Constitution Bench — ModificationGayatri Balasamy v. ISG Novasoft Technologies Ltd.Supreme Court of India | 2025 INSC 605 | 30 April 2025
Courts have a limited power under Sections 34 and 37 to modify an award: by severing the invalid portion where the award is severable; by correcting clerical, computational or typographical errors apparent on the face of the record; by modifying post-award interest in some circumstances; and under Article 142, with great care and caution.
Read judgment on Indian Kanoon →
Constitution Bench — NeutralityCentral Organisation for Railway Electrification v. ECI-SPIC-SMO-MCML (JV)Supreme Court of India | 2024 INSC 857 | 8 November 2024
Equal treatment of parties applies at the stage of appointment. A clause allowing one party to unilaterally appoint a sole arbitrator gives rise to justifiable doubts about independence; unilateral appointment clauses in public-private contracts violate Article 14. The law applies prospectively to appointments made after the judgment.
Read judgment on Indian Kanoon →
Landmark — ArbitrabilityVidya Drolia v. Durga Trading CorporationSupreme Court of India (Three Judges) | 14 December 2020
Landlord-tenant disputes governed by the Transfer of Property Act are arbitrable, but those covered by rent control legislation, where specific courts have exclusive jurisdiction, are not. The judgment also lays down the tests for non-arbitrability.
Read judgment on Indian Kanoon →
Landmark — Unilateral AppointmentPerkins Eastman Architects DPC v. HSCC (India) Ltd.Supreme Court of India | AIR 2020 SC 59 | 26 November 2019
A person who has an interest in the outcome or decision of the dispute must not have the power to appoint a sole arbitrator; this is the essence of the 2015 amendments.
Read judgment on Indian Kanoon →

Key Terms Explained

Arbitral Tribunal
A sole arbitrator or a panel of arbitrators (Section 2(1)(d)); the number must not be even (Section 10).
Seat of Arbitration
The juridical home of the arbitration, which decides which courts supervise it.
Ad hoc Arbitration
Arbitration conducted by the parties and tribunal without an administering institution.
Institutional Arbitration
Arbitration administered by an institution under its rules, such as DIAC.
Kompetenz-Kompetenz
The tribunal’s power to rule on its own jurisdiction, including the validity of the arbitration agreement (Section 16).
Interim Measure
Protective orders such as injunctions, attachment or receiver, granted by the Court (Section 9) or the tribunal (Section 17).
Patent Illegality
A ground to set aside a domestic award where the illegality appears on the face of the award (Section 34(2A)).
Fast-Track Procedure
A procedure on written pleadings without oral hearing unless required, with the award due within six months of the tribunal entering upon the reference (Section 29B).

Frequently Asked Questions

No. Section 7(3) requires an arbitration agreement to be in writing, though writing includes letters, e-mails and other electronic communication that record the agreement, or pleadings in which one side alleges it and the other does not deny it.

You can file it, but if the other side applies under Section 8 not later than its first statement on the substance of the dispute, the court must refer the parties to arbitration unless prima facie no valid arbitration agreement exists.

If a party fails to appoint within 30 days of a request, or the parties cannot agree on a sole arbitrator within 30 days, apply under Section 11 to the High Court (or the Supreme Court in international commercial arbitration) or its designated institution.

In domestic arbitration, pleadings should close within six months of the tribunal’s appointment and the award should be made within twelve months after that, extendable by six months by consent and further only by the Court.

The Supreme Court has held that a person interested in the outcome cannot unilaterally appoint a sole arbitrator (Perkins Eastman, 2019), and the Constitution Bench in CORE (2024) held unilateral appointment clauses in public-private contracts violate Article 14 for appointments after 8 November 2024.

Three months from the date of receiving the award (or from disposal of a Section 33 request), extendable by up to thirty days for sufficient cause, but not thereafter (Section 34(3)).

No. Under Section 36(2), the filing does not by itself make the award unenforceable; the Court must grant a stay on a separate application, usually on conditions such as deposit.

Disputes under the Transfer of Property Act are arbitrable, but disputes governed by rent control laws where a specific court has exclusive jurisdiction are not (Vidya Drolia, 2020).